Soth Pars Combined Cycle Power Plant -Six HRSG Units

Project Info

  • Client: Farab Construction Co. (Notash Afra Co.)
  • Location: Assaluye
  • Project: Soth Pars Combined Cycle Power Plant -Six HRSG Units
  • Progress: Completed – (2020- 2021)
  • Scope: Installation, Test and Commissioning of Electrical, Instrumentation and Control equipment of HRSG Boilers of Soth Pars Combined Cycle Power Plant

Specification:

The scope of work was the installation of all electrical and instrumentation equipment of HRSG boilers including cabling accessories, MV/LV and control cables and installation and commissioning of power and control cubicles, industrial buildings electrical equipment and accessories, and field instrument and commissioning of all executed equipment and start-up of the plant in cooperation with client