Persian Golf Gas Condensate Refinery -360,000 Barrel/Day







Project Info
- Client: Farab Construction Co. (Notash Afra Co.)
- Location: Bandar Abbas
- Project: Persian Golf Gas Condensate Refinery -360,000 Barrel/Day
- Progress: Completed – (2015- 2019)
- Scope: Pre-commissioning and site test of electrical and Instrumentation equipment in Bandar
Abbas Gas Condensate Refinery Project and performing all required ICAPS activities
Specification:
This consist of all 23 substations of the project, which includes more than 170 Power and Distribution Transformers, more than 3500 LV/MV and control cubicles In addition to substation activities, Pre-commissioning and site test for field equipment in utility areas, which includes more than 250 MV/LV motors and their local control boxes and also more than 3500 instrumentation devices are our scope of work.